Verity Rosa – progress of the construction works
Building A1 – construction shell structure; completion of roof insulation works and sanitary and electric installation works; interior finishing works and elevation works in progress
Building A2 – construction shell structure; completion of roof insulation works and sanitary and electric installation works; interior finishing works and elevation works in progress
Building A3 – construction shell structure; completion of roof insulation works and sanitary and electric installation works; interior finishing works and elevation works in progress
Building A4 – construction shell structure; completion of roof insulation works and sanitary and electric installation works; installation of passenger’s lift; interior finishing works and elevation works in progress
Building B – construction shell structure; completion of roof insulation works, sanitary and electric installation works; installation of passenger’s lifts and entrance doors in apartments, interior finishing works and elevation works; granite tiles floor works in progress
Building C – construction shell structure; completion of roof insulation works, sanitary and electric installation works and interior finishing works and installation of passenger’s lifts, interior finishing works; elevation works in progress
External construction works – fencing works in progress, construction of building’s entries and paving works in progress