Verity Rosa – progress of the construction works

Building A1 – construction shell structure; completion of roof insulation works; sanitary and electric installation works in progress
Building A2 – construction shell structure; completion of roof insulation works; sanitary and electric installation works in progress
Building A3 – construction shell structure; completion of roof insulation works; sanitary and electric installation works in progress
Building A4 – construction shell structure; completion of roof insulation works; sanitary and electric installation works in progress
Building B – construction shell structure; completion of roof insulation works, sanitary and electric installation works; interior finishing works and elevation construction works in progress
Building B – construction shell structure; completion of roof insulation works, sanitary and electric installation works